Concrete Channel / Drainage Flume Calculator

Enter your channel profile, wall thickness, and run length to instantly calculate concrete volume in cubic yards, wetted perimeter, and total material cost.

Free to use No sign-up required Rectangular, U-shape & trapezoidal profiles Imperial & metric supported
✓ Cubic yards & cubic meters ✓ Flow capacity (Manning) & wetted perimeter ✓ Cost estimator included ✓ Last verified October 2026

Written by Rachel Sousa — concrete area by exact geometry for each profile, Manning's n from Chow's Open-Channel Hydraulics, and lining checks from NRCS conservation practice standard 428, October 2026.

Enter Your Channel Dimensions

Inside clear width at the floor. For a U-shape, the inside width, which is also the diameter of the round invert. Enter a width greater than 0, up to 30 ft.
Inside depth from the channel floor (or the bottom of the invert) to the top of the walls. Enter a height greater than 0, up to 20 ft — for a U-shape, at least half the width.
Lining thickness measured square to the wall face (and around the invert of a U-shape). NRCS sets 3½ in as the minimum for plain concrete in rectangular ditch sections.
Enter a thickness from 1 in to 3 ft.
Thickness of the floor slab, if it differs from the walls. Not used for a U-shape. Enter a thickness from 1 in to 3 ft, or leave it blank.
Total length of channel from inlet to outlet. Work headwalls, drops and inlet boxes separately. Enter a length greater than 0, up to 50,000 ft.
Normal values for concrete-lined channels from Chow, Open-Channel Hydraulics (1959).
Longitudinal fall: 0.5% is 6 in per 100 ft. Enter it to see flow capacity and velocity. Enter a slope above 0, up to 50%, or leave it blank.
Water depth for the capacity check. Leave blank for the channel flowing full to the top of the walls. Enter a depth greater than 0 and no more than the channel height.
Added once to the total. Blank or 0 for the exact volume. Enter a waste factor from 0 to 50%.
$
Your ready-mix supplier's delivered price. Leave blank to skip the cost. Enter a price of 0 or more, or leave it blank.

Results appear instantly and update as you type. No sign-up required.

Your Channel Concrete Estimate

—
Cubic Yards (yd³)
—
Cubic Feet (ft³)
—
Cubic Meters (m³)
—
Wetted Perimeter (ft)
—
Interior Liner Area (ft²)
—
Channel Run (lin. ft)
— Flow Capacity (Manning)
— Velocity
— Flow Area
— Cross-Section (ft²) concrete per foot of run
— Wall Thickness
— Profile
— Waste Factor
— Concrete Weight
— Truck Loads

—

Concrete material cost only. Excavation, base, forming, joints, labor and finishing are extra. Use our Full Project Estimator for a complete breakdown.

B = bottom width, H = inside height, t = wall thickness (square to the face), tb = floor thickness, z = side slope (H:V)
Rectangular / Trapezoidal: Concrete area = (H + tb) × [B + z(H − tb) + 2t√(1 + z²)] − (B + zH) × H
  (z = 0 gives the rectangle: (B + 2t)(H + tb) − BH)
U-Shape (invert radius R = B ÷ 2): Concrete area = 2t(H − R) + π ÷ 2 × [(R + t)² − R²]

Volume (ft³) = Concrete area (ft²) × Run length (ft); Cubic Yards = ft³ ÷ 27
Final Volume = Volume × (1 + waste% ÷ 100)

Flow: A = flow area and P = wetted perimeter at the design depth; R = A ÷ P
Manning (US units): Q (cfs) = 1.486 ÷ n × A × R^(2/3) × S^(1/2); V = Q ÷ A

How to Use This Concrete Channel Calculator

  1. Choose your channel profile. Select Rectangular, Trapezoidal, or U-Shape at the top of the calculator. Rectangular suits narrow channels between walls; trapezoidal is the usual shape for lined ditches and swales cut into soil; a U-shape has a round invert, as in many precast flumes.
  2. Measure inside dimensions, not outside. The width and height fields take inside clear dimensions — the opening you see looking down into the channel. For a trapezoid, the width is the floor, not the top opening. For a U-shape, the width is the inside width, which is also the diameter of the round invert.
  3. Enter the wall and floor thickness. Enter the lining thickness from your drawing, measured square to the wall face. If the floor slab is a different thickness, enter it separately. For irrigation ditches, NRCS practice standard 428 sets 3½ in as the minimum for plain concrete in rectangular sections; trapezoidal ditch linings may be thinner by velocity and climate.
  4. Enter run length and order from results. Enter the run length and order from the cubic-yard result. To check capacity, enter the channel slope and pick the surface finish; add a design flow depth or leave it blank for the channel flowing full. The calculator gives flow in cfs, gpm and L/s and the velocity.

⚠ Pro Tip: Always calculate concrete volume from the lining area — never from the outside footprint alone. Multiplying the outside width by the outside depth counts the open flow area as concrete: on a 24 × 18 in channel with 6 in walls that doubles the figure (6.00 ft² instead of 3.00 ft² per foot).

Concrete Channel Volume Formula

The concrete volume for a channel liner is the cross-sectional area of the concrete shell multiplied by the run length. For a rectangular channel, the shell is a U-shaped frame: the outer rectangle minus the opening.

Step Formula Example: 24 in wide × 18 in deep × 6 in walls × 50 ft run
1. Convert all dims to feetinches ÷ 12B=2 ft, H=1.5 ft, t=0.5 ft, L=50 ft
2. Gross outer area(B+2t) × (H+t)(2+1) × (1.5+0.5) = 3×2 = 6.00 ft²
3. Inner void areaB × H2 × 1.5 = 3.00 ft²
4. Concrete cross-sectionGross − Void6.00 − 3.00 = 3.00 ft²
5. Volume (ft³)Area × Run Length3.00 × 50 = 150.0 ft³
6. Cubic yardsft³ ÷ 27150.0 ÷ 27 = 5.56 yd³
7. Add waste (10%)Volume × 1.105.56 × 1.10 = 6.11 yd³

Common Channel Size Reference Table

Concrete volumes for rectangular channels — 6-inch wall thickness, no waste factor. Add 10% for real-world ordering.
Inside Width × Depth Run Length Concrete Area (ft²) Volume (yd³)
12 in × 12 in50 ft2.00 ft²3.70 yd³
18 in × 18 in50 ft2.75 ft²5.09 yd³
24 in × 18 in50 ft3.00 ft²5.56 yd³
24 in × 24 in50 ft3.50 ft²6.48 yd³
36 in × 24 in50 ft4.00 ft²7.41 yd³
24 in × 18 in100 ft3.00 ft²11.11 yd³
36 in × 24 in100 ft4.00 ft²14.81 yd³
48 in × 36 in100 ft5.50 ft²20.37 yd³

All values assume 6-inch uniform wall and floor thickness, rectangular profile, no waste factor applied. Concrete area = (B + 1 ft) × (H + 0.5 ft) − B × H.

What Wall Thickness Does a Concrete Channel Need?

There is no single standard thickness for concrete channels. For irrigation ditches and canals, NRCS conservation practice standard 428 sets minimums for plain (unreinforced) concrete linings; drainage channels in a road or site plan follow that agency's standard drawing; and anything carrying traffic or large water loads needs an engineer's design.

Published minimums for plain concrete ditch linings (NRCS) and where other channels get their thickness.
Channel Application Thickness Concrete Source / Notes
Irrigation ditch, rectangular section3½ in minimum—NRCS CPS 428 (plain concrete)
Irrigation ditch, trapezoidal or parabolic1.5–3.0 in minimum—NRCS CPS 428 Table 2: by design velocity (up to 15 ft/s) and cold or warm climate
Ditch lining (construction specification)Per design3,000 psi at 28 days; 5–7% airNRCS Wyoming spec WY-428-A; contraction joints at 10 ft average
Roadside or site drainage channelPer agency standard drawingPer specificationCity, county or DOT detail
Traffic-loaded, covered or grated channelEngineer's designPer designCovers and gratings carry wheel loads into the walls
Large flume or drop structureEngineer's designPer designUplift, sliding and hydraulic jump need analysis

For any channel that will have grating, hatches, or covers placed over it, the walls carry the cover loads — size them in the design rather than from a liner minimum.

Common Mistakes When Estimating Concrete Drainage Channels

Frequently Asked Questions

Worked Examples

Five channels worked by hand. Enter the same inputs and the calculator will match.

Example 1: Rectangular 24 × 18 in, 6 in walls and floor, 50 ft, 10% waste

(3 × 2) − (2 × 1.5) = 3.00 ft². 3.00 × 50 = 150.0 ft³ = 5.56 yd³; with waste 6.11 yd³.

Example 2: Trapezoidal: 3 ft floor, 2 ft deep, 1.5:1 sides, 4 in lining, 200 ft, no waste

√(1 + 1.5²) = 1.803. Outer area = 2.333 × [3 + 1.5 × (2 − 0.333) + 2 × 0.333 × 1.803] = 15.638 ft²; opening (3 + 3) × 2 = 12.000 ft². Concrete 3.638 ft² × 200 = 26.95 yd³. (The old formula gave 4.722 ft².)

Example 3: U-shape: 24 in wide, 24 in deep, 4 in walls, 100 ft, no waste

R = 1 ft. 2 × 0.333 × (2 − 1) + π ÷ 2 × (1.333² − 1²) = 1.888 ft². × 100 = 6.99 yd³.

Example 4: Rectangular 24 × 18 in, 6 in walls, 8 in floor, 50 ft, no waste

(2 + 1) × (1.5 + 0.667) − 3.00 = 3.500 ft². × 50 = 6.48 yd³.

Example 5: Capacity: 4 ft floor, 1.5:1 sides, 1.5 ft flow depth, 0.2% slope, float finish

A = 1.5 × (4 + 1.5 × 1.5) = 9.375 ft²; P = 4 + 2 × 1.5 × 1.803 = 9.408 ft; R = 0.996 ft. Q = 1.486 ÷ 0.015 × 9.375 × 0.996^(2/3) × 0.002^(1/2) = 41.4 cfs, 4.42 ft/s.

Calculator Assumptions, Sources and Limits

The concrete quantities are exact for the profile entered; the capacity is uniform flow by Manning's equation. The calculator does not size a channel for a storm, check structural strength, or design joints.

Values used by the calculator and where they come from.
ItemValueSource or Basis
Trapezoid / rectangleLining offset square to each face by t, floor by tb; outer corner where the two offsets meet; flat tops at the wall heightGeometry
U-shapeRound invert of radius = half the inside width, uniform thickness, straight walls aboveGeometry; a flat-bottomed outer shape uses more concrete
Manning's n0.013 trowel, 0.015 float, 0.017 unfinished (normal values)Chow, Open-Channel Hydraulics (1959), concrete-lined channels
Manning constant1.486 for US units (ft, s)Standard form of Manning's equation
Lining checks3½ in minimum (rectangular), 3 in freeboard, 15 ft/sNRCS conservation practice standard 428, Irrigation Ditch Lining
Weight and loads150 lb/ft³; 10 yd³ per truckSite-wide figures
Accepted inputsWidth up to 30 ft; height up to 20 ft; thickness 1 in to 3 ft; side slope 0–6; slope up to 50%; run up to 50,000 ft; waste 0–50%Outside these the field shows an error instead of a result.

For curbs with a gutter pan, use the Curb and Gutter Calculator.

The people behind this calculator

Rachel Sousa
Rachel Sousa · Writer

B.S. Civil Engineering, Purdue University. 10+ years turning construction and engineering standards into clear, usable calculator documentation; former documentation lead at a national ready-mix supplier.

Related Concrete Calculators