Concrete Project Planner

Enter your project details and get a realistic phase-by-phase timeline — from site prep through full 28-day cure — adjusted for project size, crew, and season.

Free to use No sign-up required Curing periods follow ACI 308R 6 project phases tracked
✓ Gantt-style visual timeline ✓ Season & temperature adjustments ✓ Crew size and days off factored in ✓ Last verified October 2026

Written by Rachel Sousa — curing periods and weather limits checked against ACI 308R, ACI 306R-16 and ACI 305.1-14, October 2026.

Enter Your Project Details

Sets how long forming takes. Footing forms are left on a day longer.
Total surface area of the slab or pour. Enter an area greater than 0, up to 100,000 sq ft (9,290 m²).
4 in for patios and walkways, 4–6 in for driveways. Sets the concrete volume, truck loads and bag count. Enter a thickness from 1 to 60 in (25 to 1,524 mm).
Larger crews shorten site prep, forming and bag mixing.
Use the lowest temperature expected on pour day and the week after. Below 40°F is cold-weather concreting under ACI 306R.
Bagged concrete is counted at about 1 cubic yard (45 80-lb bags) a day for two people.
Adds the permit wait, in business days, before site work begins.
5–10 business days is typical. Ask your building department for its current turnaround. Enter a wait from 0 to 120 business days.
Site work skips the days off. Curing carries on every day.
Adds calendar dates to every phase and milestone. With a permit, this is the day you apply.

Results appear instantly and update as you change the inputs. Planning estimate — confirm cure times with your concrete supplier.

Your Project Timeline

✅ Mild conditions
—
Total Calendar Days
—
Active Work Days
—
Pour Day (Day #)
MilestoneDayDate
— Project Area
— Crew Size
— Season
— Supply Method
— Concrete Volume
— To Order
— Work Week
— Start Date
Site Prep (work days) = CEIL(area_sqft ÷ (200 × crew_factor))
Forming (work days) = CEIL(area_sqft ÷ (300 × crew_factor) × project_factor)
Pour = 1 day (ready-mix) or CEIL(volume_ft³ ÷ (26.7 × crew_factor)) days (bagged)
crew_factor: 1 person 0.5, 2 people 1.0, 3–4 people 1.6, 5+ people 2.4
Cure times count from the last pour day, in calendar days, × temp_multiplier (mild 1.0, hot 1.0, cool 1.5, cold 2.0), rounded up:
  Foot traffic and form stripping: 2 days (footing forms 3 days)
  Minimum curing, cars and light pickups: 7 days
  Design strength, heavy loads, sealing: 28 days
Permit: the business days entered, Monday to Friday, before site prep
Site work skips the days off in the work week chosen; curing counts every day
Total Calendar Days = day number on which design strength is reached
Active Work Days = site prep + forming + pour + 1 day to strip forms

How to Use This Concrete Project Planner

  1. Select your project type and enter the area. Pick the closest match to your project from the dropdown — this sets how long forming takes. Enter the total pour area in square feet or square meters, and the slab thickness. For a driveway that's 20 ft × 40 ft, enter 800 sq ft. The thickness gives the concrete volume, the number of truck loads or bags, and how many days a bagged pour takes.
  2. Set your crew size and season. A solo DIYer takes significantly longer on site prep and forming than a 3-person crew. Season matters just as much: cool weather stretches every cure time by 50% and cold weather below 40°F doubles it and calls for blankets or a heated enclosure. Hot weather shortens the time you have to place and finish, so pour early in the morning.
  3. Choose your concrete supply method. Ready-mix is poured in one continuous pour; your pour day is fixed and fast. Bagged concrete mixed on site can stretch a large pour over multiple days, introducing the risk of cold joints if phases aren't managed carefully. For anything over 1 cubic yard, ready-mix is almost always the right call.
  4. Read your timeline and plan around the non-negotiables. The curing times are not flexible — no cars for at least 7 days after the pour and no heavy loads for 28, longer in cool weather. Use the active work days figure to schedule labor, and the pour day to schedule your ready-mix delivery. Reserve the delivery slot as soon as you know the pour date, because plants book up in peak season, and confirm it only when the forms are finished. Set your work days and a start date to turn the day numbers into calendar dates.

⚠ Pro Tip: The pour day is your point of no return. Ready-mix has a working life of roughly 60 to 90 minutes from the time it is batched at the plant, and the drive to your site comes out of that. Have every form set, every rebar tied, every tool staged, and every extra hand confirmed before you call the plant to dispatch. A half-prepared pour site is one of the most expensive mistakes in residential concrete.

How the Concrete Project Timeline Is Calculated

Each working phase has a base duration from a planning production rate for a two-person crew, adjusted for crew size and supply method. Cure times run from the last pour day and are adjusted for temperature. The table below shows the worked example for a 400 sq ft residential patio with a 2-person crew in mild conditions using ready-mix.

Phase Duration Logic Example (400 sq ft, 2 crew, mild weather)
Site Prep & ExcavationCEIL(area ÷ (200 × crew_factor))CEIL(400 ÷ 200) = 2 days (Days 1–2)
Forming & RebarCEIL(area ÷ (300 × crew_factor) × project_factor)CEIL(400 ÷ 300 × 1.0) = 2 days (Days 3–4)
Pour Day1 day (ready-mix) or CEIL(volume ÷ 26.7 ft³ × 1 ÷ crew_factor) days (bagged)1 day (Day 5)
Initial Cure (walk-on)2 days × temp_multiplier2 × 1.0 = 2 days (foot traffic Day 7)
Strip Forms1 work day, 2 days after the pour × temp_multiplierDay 7
Cars and light pickups7 days after the pour × temp_multiplierDay 12
Full Cure (heavy loads)28 days after the pour × temp_multiplier28 days (Day 33)

Quick-Reference Timeline by Project Type

Day numbers from the first day on site. Mild conditions, ready-mix, working every day, no permit, 4 in slab.
Project Type Area Crew Active Work Days Pour Day Cars Allowed Full Cure Complete
Small Patio / Pad200 sq ft2 people4 daysDay 3Day 10Day 31
Standard Patio400 sq ft2 people6 daysDay 5Day 12Day 33
Residential Driveway600 sq ft2 people8 daysDay 7Day 14Day 35
Residential Driveway600 sq ft3–4 people6 daysDay 5Day 12Day 33
Large Driveway800 sq ft3–4 people7 daysDay 6Day 13Day 34
Large Garage Floor1,200 sq ft3–4 people9 daysDay 8Day 15Day 36
Commercial Slab (small)2,000 sq ft5+ people12 daysDay 11Day 18Day 39

A permit adds its wait in business days before Day 1 of site work: 7 business days is 9 calendar days from a Monday. Cure times are 50% longer between 40 and 50°F and double below 40°F.

How Season Affects Your Concrete Timeline

Temperature is the single biggest variable in concrete scheduling that most homeowners underestimate. The table below shows the real-world impact on each phase.

Temperature effects on concrete project timeline. Set times are approximate, for a plain mix without accelerators or retarders.
Condition Temp Range Pour Window Approx. Set Time Cure Adjustment Special Requirements
Mild50–80°F (10–27°C)Any time of dayAbout 6 hours at 70°F; 4 at 80°F, 10 at 50°FNone — use baselineCuring compound, wet burlap or plastic sheeting for 7 days
HotAbove 80°F (27°C)Early morningUnder 4 hours; under 3 at 90°FNone, but curing must start at onceShade, windbreaks, fog spray, dampened subgrade; concrete at or below 95°F (35°C) at discharge
Cool40–50°F (4–10°C)Midday (warmest hours)About 10–15 hours× 1.5 on all cure timesInsulating blankets overnight; never place on frozen ground
ColdBelow 40°F (4°C)Only with a cold-weather plan15–19 hours or more× 2 on all cure timesACI 306R protection: heated mix, blankets or a heated enclosure until the concrete reaches 500 psi

ACI 306R treats a pour as cold-weather work when the air temperature is at, or expected to fall below, 40°F (4°C) during the protection period. Fresh concrete must not freeze until it reaches about 500 psi, which takes about 48 hours when the concrete is kept at 50°F. Concrete that freezes sooner can lose up to half of its ultimate strength, and later curing does not bring it back. Check the overnight lows for the first two nights, and have blankets on site before the truck arrives.

Common Timeline Mistakes on Concrete Projects

Frequently Asked Questions

Worked Examples

Three timelines worked by hand. Enter the same inputs in the planner and the results will match.

Example 1: a 400 sq ft patio, two people, mild weather

Ready-mix, 4 inches thick, no permit, working every day. Site prep is 400 ÷ 200 = 2 days (Days 1–2). Forming is 400 ÷ 300 = 1.33, rounded up to 2 days (Days 3–4). The pour is Day 5 and takes 133 ft³, or 4.94 yd³, which is one truck load. Foot traffic and form stripping fall 2 days later on Day 7. Minimum curing ends and cars are allowed 7 days after the pour, on Day 12. Design strength is reached 28 days after the pour, on Day 33. Active work days: 2 + 2 + 1 + 1 = 6.

Example 2: a 600 sq ft driveway with a permit, in cool weather, with dates

Five inches thick, a crew of 3–4, ready-mix, Monday to Friday, a 7-business-day permit and a start date of Monday, March 1, 2027. The permit takes March 1–9. Site prep is 600 ÷ (200 × 1.6) = 1.9, so 2 days: March 10–11. Forming is 600 ÷ (300 × 1.6) × 1.1 = 1.4, so 2 days: Friday, March 12 and Monday, March 15. The pour is Tuesday, March 16 (Day 16) and needs 9.26 yd³. Cool weather multiplies cure times by 1.5: foot traffic and forms off after 3 days on March 19, cars after 11 days on March 27, and design strength after 42 days on Tuesday, April 27 (Day 58).

Example 3: a 10 × 12 ft shed pad mixed from bags by one person

The pad is 120 sq ft at 4 inches: 40 ft³, or 67 80-lb bags. One person is counted at half the two-person rate. Site prep is 120 ÷ 100 = 1.2, so 2 days. Forming is 120 ÷ 150 = 0.8, so 1 day. Mixing 40 ft³ at 13.3 ft³ a day takes 3 days (Days 4–6), with a planned joint at the end of each day. Cure times count from the last pour day: foot traffic on Day 8, cars on Day 13 and design strength on Day 34. A single ready-mix delivery would cut the pour to one day and remove the joints.

Planner Assumptions, Sources and Limits

The planner is a scheduling estimate. These are the rates and rules behind it, so you can see where your own job differs.

Rates and rules used by the planner, and where they come from.
ItemValueSource or Basis
Site prep rate200 sq ft per day for two peoplePlanning allowance for excavating, grading, compacting and placing a gravel base with hand tools and a plate compactor. A mini excavator or skid steer is faster.
Forming rate300 sq ft per day for two people, times a project factorPlanning allowance for forms and reinforcement. Factors: walkway 0.9, patio 1.0, driveway 1.1, garage floor 1.15, footing 1.4, commercial slab 1.5.
Crew factor1 person 0.5; 2 people 1.0; 3–4 people 1.6; 5+ people 2.4Output rises with crew size but less than in proportion.
Ready-mix pour1 dayOne continuous placement. Truck loads are counted at 10 yd³.
Bagged pour26.7 ft³ per day for two people (about 1 yd³, or 45 80-lb bags)Planning allowance with a mixer. An 80-lb bag yields 0.60 ft³.
Foot traffic and form stripping2 days after the pour (footing forms: 3 days)The usual 24–48 hours for slab edge forms in mild weather.
Minimum curing7 daysACI 308R curing guidance; ACI 318 requires 7 days at 50°F or above for normal mixes.
Cars and light pickups7 days after the pourConcrete is at roughly 70% of design strength at 7 days in normal conditions.
Design strength28 days after the pourThe age at which specified compressive strength is tested (ASTM C39).
Mild and hot weatherCure times × 1.0Heat speeds up early strength but does not raise later strength, so the 28-day figure is not shortened. ACI 305.1 limits concrete to 95°F (35°C) at discharge.
Cool weather, 40–50°FCure times × 1.5Nurse–Saul maturity function with a −10°C datum: concrete held at 50°F gains strength at two-thirds of the rate at 68°F.
Cold weather, below 40°FCure times × 2The same function at 40°F. ACI 306R-16 defines cold weather as air at or expected to fall below 40°F and requires protection from freezing until the concrete reaches 500 psi.
Permit waitBusiness days, Monday to Friday; default 7Typical turnaround is 5–10 business days and varies by office.
CalendarSite work skips days off; curing counts every dayCure clocks start on the last pour day. Without a start date, Day 1 is taken as a Monday.
Unit conversion1 m² = 10.7639 sq ft; 1 in = 25.4 mmExact definitions.
Accepted inputsArea above 0, up to 100,000 sq ft (9,290 m²); thickness 1 to 60 in; permit wait 0 to 120 business daysOutside these the field shows an error instead of a timeline.

What the planner does not include

For the background, see the guide to concrete curing and the guide to concrete delivery costs. To work out how much concrete to order, use the concrete slab calculator. For cure times at a specific temperature, use the concrete curing time estimator, and for sealing after the cure, the concrete sealer coverage calculator.

The people behind this calculator

Rachel Sousa
Rachel Sousa · Writer

B.S. Civil Engineering, Purdue University. 10+ years turning construction and engineering standards into clear, usable calculator documentation; former documentation lead at a national ready-mix supplier.

Related Calculators